School Toilet Refurbishment During Term Time
We are currently carrying out this school toilet refurbishment during term time. After providing a competitive quotation to refurbish five toilet blocks at this school, the business manager asked if we could complete the works during the school summer holidays. Unfortunately we were already fully booked. However we suggested that we could carry out the works during term time after the holidays had finished. After consideration and the submission of a full programme of works, the school agreed to have the works carried out during term time with the inclusion of two half term holidays being added.
Waller Services – Safeguarding
Due to the amount of projects that we carry out within the education sector, we understand the importance of safeguarding in schools. All of our staff and contractors hold enhanced DBS certificates which are renewed every three years. In addition, we have a password protected area of our website where schools can view the information of anyone that we send to work in schools. Along with the relationship that we have previously built up with the school, the importance we place in safeguarding was a key factor of us being able to work in the school whilst students were present.
Year Three Toilet Refurbishment
Working closely with the school and providing daily updates, we were able to start the first part of the project in September. We ripped out the existing year 3 toilets, after school hours, and securely sectioned off the area. The existing facilities were separate boys and girls toilets. The school requested that we produce one larger space to provide a more open plan, unisex toilet block. This was achieved by removing a wall and the two entrance doors. New floor to ceiling privacy cubicles were installed with new suspended ceiling incorporating new LED lighting being added. We also laid new flooring and installed whiterock hygiene cladding to the walls. The final touch was two hand washing troughs.
October Half Term
We are currently ripping out the Year 1 and Beech Boys toilet areas. Both toilet blocks will be fully refurbished with the works completed one week after half term.
February Half Term
The final part of the project will be carried out before, during and after the February half term.
In a joint effort with the school, our contract manager and contractors, the works have gone very smoothly even during term time.
For more projects similar to this one, please click on the following link https://www.wallerservices.com
Building Services We Provide In Schools
The building services we provide include smaller refurbishments through to extensions and new builds. The services we provide include anything that a school would require. This includes, toilet and kitchen refurbishments. We also install fencing, flooring and carry out complete new builds. Check out our website case studies to view projects that we have recently completed.
Glazing Services We Provide In Schools
In addition to building works, we also carry out works from window and hinge repairs through to complete aluminium and uPVC window and door installations.
Contact Waller Building and Glazing Services
Based in Sittingbourne, we carry out works Kent as well as the south east of England. If you would like a quotation on any size of building or glazing project please contact us. Telephone – 01795 424435. Additionally email mark@wallerservices.com
To check out what we are up to at the moment visit our Facebook page https://www.facebook.com/profile.php?id=100063701672876
As well as this, see what we are tweeting https://twitter.com/BuildingOnTrust